Item

Description of Check

1 TEST CONDITION : Prior to this test, follings to be completed as practical as possible.
1) Oily water to be ready in bilge holding tank.
2) Oily water separator and the related apparatus to be ready in operation.
2 Working pressure
3 PPM SENSOR "0" SETTING.
4 PPM SENSOR 의한 3-WAY VALVE 작동상태.
5 OIL LEVEL HIGH SENSOR 의한 2-WAY VALVE 작동상태.
6 SAFETY VALVE POPPING.
7 BILGE HOLDING TANK LEVEL SWITCH 의한 AUTO START/STOP.
8 EM'CY STOP.
9 TEST PROCEDURE : Inorder to set zero.
1) The clean oil free water to be led through the respective connection into the measuring cell.
2) After 2-3 miniature, set Zero by adjusting the potentiometer screw VR4 in oil alarm unit.
3) Confirm zero setting
10 Inorder to inspect the Oil Content Meter function.
1) Sampling bottle to be connected to the respective connection.
2) Oily water separater to be in service within 15 ppm and then the sampling water is to be led through the 15 ppm alarm unit.
3) Confirm that the oily water recirculates into bilge holding tank by checking the solenoid v/v.
11 In order to prove the oil Level Function
1) Detach the Oil Level sensor from the oily water separator. (Oily Water Separator is not to be in service this time)
2) Put this sensor into the sampling bottle made specially for this inspection.
3) Confirm that the solenoid valve fitted on discharge line actuates.
4) Make it back to normal condition.
12 In order to stop the pump
  The float is to be operated by either an extension rod or an equivalent.
 